FAQ
Questions about ERP for pipes & tubes
What is the best ERP for pipe manufacturing?
Look for batch, heat and lot traceability from resin or coil, production by line or mill,
weight-length control, scrap tracking, test records and heavy dispatch. Pothera covers each
of these for plastic and steel pipe plants.
What is the PVC pipe manufacturing process?
Resin is mixed with stabilisers, fillers and pigments, extruded through a die, sized and
cooled, printed, cut to length, socketed and tested before bundling.
How are ERW pipes made?
Steel coil is slit into strips, formed into a tube and joined by electric resistance
welding, then sized, cut, tested, and for GI pipes galvanised and threaded.
What raw materials are used in PVC pipe manufacturing?
PVC resin plus stabilisers, lubricants, fillers such as calcium carbonate, and pigments.
Pothera tracks each by batch at receipt.
Can Pothera track stock by both weight and length?
Yes. Pothera automates weight calculations, so stock and production can be seen by weight
and by length for each size.
Can Pothera trace a pipe back to the coil or resin batch?
Yes. Batch, heat and lot numbers are carried from goods receipt through production stages to
the finished bundle.
How does Pothera handle scrap and regrind?
Scrap items and production loss are defined on the BOM, actual scrap is recorded per order,
and regrind can be re-processed as its own order.
Can galvanising be done through job workers?
Yes. Pipes sent for galvanising, threading or coating go out on job work challans and are
reconciled when they return.
Does Pothera manage truck loading and gate passes?
Yes. Dispatch coordination includes gate pass management, truck loading and delivery
scheduling.
How long does implementation take for a pipe plant?
Typically 8–12 weeks, depending on the number of lines or mills, sizes and classes, and
locations.